Introduction:
The Jammu & Kashmir and Ladakh High Court has held that a public corporation cannot unilaterally impose financial penalties upon a private contractor or alter the agreed contractual arrangement by relying upon decisions of an internal committee when the governing agreement does not authorise such action. The Court clarified that an administrative policy formulated to ensure uniformity in dealing with contractors cannot, by itself, modify existing contractual obligations or create additional financial liabilities without the consent of the contracting parties.
A Division Bench comprising Justice Sanjeev Kumar and Justice Mohd. Yousuf Wani delivered the judgment while allowing an intra-court appeal filed by M/s Alpine Agro Services against the Food Corporation of India (FCI). The Bench set aside the Single Judge’s decision dismissing the firm’s writ petition and quashed the recovery notices issued by the Corporation on the basis of decisions taken by its High Level Committee.
The dispute arose under the Private Entrepreneur Guarantee (PEG) Scheme, pursuant to which Alpine Agro Services was awarded a contract for the construction and operation of a godown with a storage capacity of 17,500 metric tonnes at Shilvat. The facility was taken over by the FCI on a Guaranteed Hiring Basis from February 2015.
Under the contractual arrangement, the appellant had undertaken to complete the drainage work by March 2015 and the black-topping of internal roads by September 2015. The deadline for completing the black-topping work was subsequently extended until February 26, 2016. However, the appellant failed to complete the work within the extended period, and it was ultimately completed during May-June 2017.
The FCI initially imposed a recovery of ₹1,58,002 through an office order dated January 17, 2018, on account of the delay in completing the black-topping work. Subsequently, the Corporation issued further recovery communications dated September 3, 2021, and November 15, 2021, seeking to implement decisions of its High Level Committee concerning regulation of hiring charges and deductions based on estimated cost savings.
The appellant challenged these additional recoveries, contending that the Lease and Service Agreement did not contain any provision empowering the FCI to impose such penalties or unilaterally change the agreed hiring arrangement from Guaranteed Hiring Basis to Actual Utilization Basis.
A Single Judge of the High Court dismissed the writ petition on June 6, 2026, holding that the appellant had failed to fulfil an essential contractual obligation despite having been granted an extension of time. Aggrieved by the decision, Alpine Agro Services preferred an intra-court appeal before the Division Bench.
The central question before the appellate Bench was whether the FCI could impose additional financial recoveries upon the appellant for delayed completion of the black-topping work by relying upon decisions of its High Level Committee, despite the absence of any contractual provision authorising such penalties or alteration of the hiring arrangement.
The High Court acknowledged that the appellant had breached its contractual undertaking by failing to complete the work within the stipulated period. However, it distinguished the existence of a contractual breach from the legal authority to impose a particular financial consequence for that breach.
The Court emphasised that contractual obligations must be enforced in accordance with the terms agreed between the parties and the applicable law. An administrative decision cannot substitute for a contractual provision or create a liability that the agreement does not contemplate.
The judgment also examined the principles governing compensation for breach of contract under Sections 73 and 74 of the Indian Contract Act, 1872, as well as the doctrine of unjust enrichment under Section 70. It clarified that financial recoveries must be supported by a contractual or legal basis and cannot be imposed merely because a public corporation considers them appropriate under an internal policy.
The ruling is significant in the context of government contracts and public-sector commercial arrangements because it reinforces the principle that administrative authorities must respect contractual commitments and cannot unilaterally alter agreed terms or impose arbitrary financial burdens upon contractors.
Arguments of the Parties:
The dispute before the Division Bench primarily concerned the contractual authority of the Food Corporation of India to impose additional recoveries upon Alpine Agro Services for the delayed completion of black-topping work and to alter the agreed hiring arrangement by relying upon decisions of its High Level Committee.
The appellant, M/s Alpine Agro Services, challenged the recovery notices on the ground that the Lease and Service Agreement executed between the parties did not authorise the FCI to impose the financial liabilities in question. It contended that the Corporation could not introduce new conditions into an existing contract through an internal administrative decision without obtaining the consent of the contracting party.
The appellant acknowledged the contractual obligation to complete the internal roads and the fact that the work had not been completed within the extended period. However, its grievance was directed against the financial consequences subsequently imposed by the FCI, which it argued were not contemplated by the agreement.
Alpine Agro Services contended that the contractual relationship was governed by the agreed Guaranteed Hiring Basis, under which the Corporation was liable to pay the stipulated hiring charges for the godown in accordance with the terms of the Lease and Service Agreement. The appellant argued that the FCI could not unilaterally convert this arrangement into an Actual Utilization Basis or introduce deductions calculated according to an internal policy.
It further argued that the High Level Committee’s decisions could not be treated as binding contractual terms merely because the Corporation had formulated them to ensure uniformity in dealing with PEG Scheme contractors. Such administrative decisions could not override the terms of an agreement already executed between the parties.
The appellant also questioned the legality of the recovery notices issued in September and November 2021, contending that the amounts sought to be recovered were calculated unilaterally by the Corporation without any contractual provision prescribing the applicable penalty, the method of calculation or the circumstances in which such recoveries could be made.
Alpine Agro Services maintained that the FCI had taken possession of the godown, commenced its utilisation and continued to benefit from the facility. The Corporation had not demonstrated that the delay in black-topping the internal roads had caused it any financial loss or prevented it from utilising the godown for its intended purpose.
The appellant also relied upon the contractual provisions dealing with deficiencies and breaches. It argued that the agreement itself provided mechanisms through which the Corporation could address a failure to perform contractual obligations. If the FCI considered the delay sufficiently serious, it could have invoked the applicable clauses, taken appropriate contractual action or undertaken the remaining work and recovered the actual expenditure in accordance with the agreement.
The appellant contended that the Corporation could not bypass these contractual mechanisms and impose additional financial recoveries by relying upon a policy formulated subsequently by its High Level Committee.
It also challenged the Single Judge’s decision dismissing the writ petition, arguing that the existence of a contractual breach did not automatically validate the recovery notices. The legality of the financial liability had to be independently examined by reference to the terms of the agreement and the applicable provisions of the Contract Act.
On the other hand, the Food Corporation of India sought to justify the recoveries on the ground that Alpine Agro Services had failed to fulfil an important contractual obligation despite being granted an extension of time.
The Corporation’s position was that the appellant had undertaken to complete the black-topping of the internal roads within the stipulated period but had failed to do so. The work remained incomplete even after the extended deadline of February 26, 2016, and was completed only during May-June 2017.
The FCI argued that the delay had resulted in savings to the appellant because it had continued to receive hiring charges while the black-topping work remained unfinished. It sought to justify the financial deductions on the basis of the decisions taken by its High Level Committee, which had formulated a policy concerning hiring charges, Actual Utilization Basis and deductions linked to estimated cost savings.
The Corporation also relied upon the earlier recovery of ₹1,58,002 made through the office order dated January 17, 2018. It sought to explain that the initial recovery had been made pursuant to audit objections raised by the Comptroller and Auditor General, while the subsequent recoveries were based upon the High Level Committee’s decisions concerning the regulation of hiring charges.
The respondents further contended that allowing the appellant to retain the financial benefit arising from the non-completion of the black-topping work, while continuing to receive the full contractual rentals, would amount to unjust enrichment.
In support of this contention, the Corporation invoked Section 70 of the Indian Contract Act, 1872, which provides for compensation in certain circumstances where a person lawfully does something for another or delivers something to another, without intending to do so gratuitously, and the latter enjoys the benefit.
The FCI sought to sustain the recoveries by arguing that the appellant could not be permitted to benefit financially from its own failure to perform a contractual obligation.
The respondents also questioned the appellant’s challenge to the High Level Committee’s decisions, contending that the firm had not separately challenged the general policy formulated by the Committee.
The Division Bench was therefore required to consider whether the appellant’s contractual breach justified the financial recoveries, whether the High Level Committee’s decisions could be incorporated into the existing agreement without consent, and whether the Corporation could invoke unjust enrichment or the statutory provisions governing compensation to sustain the deductions.
Court’s Judgment:
The Division Bench allowed the intra-court appeal, set aside the Single Judge’s judgment and quashed the recovery notices issued by the Food Corporation of India. It held that the Corporation could not impose financial penalties or alter the agreed contractual hiring arrangement through decisions of its High Level Committee when the Lease and Service Agreement did not authorise such recoveries.
The Court acknowledged that Alpine Agro Services had failed to complete the black-topping work within the stipulated period, even after being granted an extension. However, it held that the existence of a contractual breach did not, by itself, confer upon the FCI an unrestricted power to impose financial liabilities without a contractual or legal foundation.
The Bench observed:
“In the absence of any specific clause in the terms and conditions of the Lease and Service Agreement executed between the appellant and the respondent-Corporation, the respondent-Corporation could not have unilaterally imposed a penalty, that too on the basis of calculations made at its own level.”
The Court’s reasoning rested upon the distinction between a party’s failure to perform a contractual obligation and the remedies legally available to the other contracting party. A breach may entitle the aggrieved party to invoke remedies provided under the agreement or under the applicable law, but it does not authorise the imposition of any financial consequence that the aggrieved party considers appropriate.
Contractual obligations cannot be modified through unilateral administrative decisions
The Court examined the nature of the High Level Committee’s decisions, which had been relied upon by the FCI to regulate hiring charges and impose deductions upon PEG Scheme contractors where black-topping work had not been completed.
It recognised that the Committee’s policy might have been formulated with the objective of ensuring uniformity in the treatment of contractors and regulating financial arrangements in similar situations. However, the objective behind an administrative policy could not determine its applicability to an existing contractual relationship.
The rights and obligations of Alpine Agro Services and the FCI were governed by the Lease and Service Agreement executed between them. The Corporation was therefore required to act within the terms of that agreement while determining the consequences of the appellant’s failure to complete the work.
The Bench held that an administrative decision cannot automatically become part of a contract merely because it has been adopted by the contracting authority. A policy or decision of an internal committee may guide the Corporation in entering into future contracts or dealing with matters within its administrative jurisdiction, but it cannot independently create additional contractual obligations for a party to an existing agreement.
The Court observed:
“The decisions of the High Level Committee, even if intended to ensure uniformity in the matter of hiring charges payable to PEG investors, cannot automatically become part of an existing contract. Unless the agreement permits such a change or the parties have agreed to it, an administrative decision cannot, by itself, create additional financial liabilities.”
This principle is particularly relevant where a public-sector corporation enters into commercial agreements with private parties. The corporation may have the authority to formulate policies for regulating its operations, but the implementation of those policies must remain consistent with existing contractual commitments.
The Court clarified that the FCI could not unilaterally introduce a new financial arrangement or impose deductions that were not contemplated by the agreement. The appellant’s consent or a contractual provision authorising such a change was necessary.
The High Level Committee’s decisions could potentially govern future Lease and Service Agreements, where the relevant conditions could be incorporated at the time of execution. However, those decisions could not retrospectively alter the agreement already executed with Alpine Agro Services.
Breach of contract does not automatically authorise imposition of a penalty
The High Court rejected the argument that the appellant’s failure to complete the black-topping work within the extended period was sufficient to justify the impugned financial recoveries.
It drew a distinction between the obligation to complete the work and the authority to impose a penalty for failing to fulfil that obligation.
The appellant had admittedly failed to complete the work by February 26, 2016, despite the extension granted by the Corporation. The work was completed only during May-June 2017. Nevertheless, the Court held that the FCI could not impose a monetary penalty merely by relying upon this breach without identifying a contractual provision or legal basis authorising the particular recovery.
A contractual breach does not give the aggrieved party an unrestricted right to determine the amount payable by the defaulting party. The financial consequences of a breach must be assessed in accordance with the remedies provided under the contract and the applicable law.
The Court therefore examined whether the Lease and Service Agreement contained any provision authorising the FCI to impose the deductions in question or to calculate a penalty according to the High Level Committee’s policy.
Upon examining the agreement, the Bench found no clause empowering the Corporation to unilaterally impose the additional recoveries or convert the agreed Guaranteed Hiring Basis into Actual Utilization Basis.
The absence of such a provision was decisive. The Corporation could not create a financial liability merely by issuing administrative directions or calculating an amount on its own.
The Court held that the appellant’s failure to perform the contractual obligation could not be used as a justification for imposing a penalty that had no contractual foundation.
Clauses 4 and 5 provided contractual remedies for deficiencies
The Division Bench also examined Clauses 4 and 5 of the Lease and Service Agreement, which provided a mechanism for dealing with deficiencies and breaches of contractual obligations.
The Court noted that the agreement contained remedies available to the FCI in the event of the appellant’s failure to fulfil its obligations. The Corporation could have invoked the relevant contractual provisions and taken appropriate action if it considered the breach sufficiently serious.
The available contractual mechanism included proceeding towards termination of the agreement where warranted by the nature of the breach. The Corporation could also undertake the necessary work itself and recover the actual expenditure incurred from the rentals payable to the appellant, subject to the terms of the agreement.
The Court found that the FCI had not demonstrated that it had invoked these contractual provisions in the manner contemplated by the agreement. Instead, it sought to impose additional recoveries by relying upon the High Level Committee’s decisions.
The Bench emphasised that the existence of contractual remedies could not be ignored in favour of a unilateral financial mechanism that was not provided for in the agreement.
Where the parties have expressly agreed upon the manner in which deficiencies or breaches are to be addressed, the contracting authority must ordinarily act within that framework. It cannot bypass the agreed mechanism and introduce an alternative remedy through an administrative policy.
This reasoning reinforces the principle that contractual remedies must be exercised in accordance with the agreement. A public corporation cannot substitute the agreed procedure with a financial consequence of its own choosing merely because the contractor has committed a breach.
FCI continued to utilise the godown without establishing financial loss
The Court also considered the circumstances in which the FCI had taken over and utilised the godown.
The appellant had completed the construction of the facility, and the Corporation had taken possession of it under the Guaranteed Hiring arrangement from February 2015. Although the internal roads had not been black-topped within the stipulated period, the FCI continued to utilise the godown.
The Bench noted that the Corporation had consciously granted an extension for completion of the work and had thereafter continued with the contractual arrangement. It had also executed a fresh Lease and Service Agreement without incorporating any additional stipulation concerning the delayed black-topping.
The Court observed that the Corporation had taken over the godown and put it to use without suffering any established financial loss on account of the delay in completing the road work.
It noted:
“The respondent-Corporation took over possession of the godown and put it to use without suffering a loss of even a penny.”
The Bench further observed that there was no pleaded case demonstrating that the unfinished black-topping workhad caused the Corporation any financial loss or prevented the optimum uti